Many companies choose to build gas engine power plants to generate electricity close to their facilities, recover waste heat, reduce energy costs, and improve overall operational efficiency.
However, these projects involve both power generation and gas supply, requiring compliance with multiple regulatory procedures and coordination among various external stakeholders. Many projects face construction delays, cost overruns, or even suspension due to insufficient preliminary assessments, improper sequencing of approval procedures, or failure to secure gas supply and grid connection conditions in advance. As a result, significant upfront investments may go to waste.
Based on real gas engine power plant projects commissioned in China, this article outlines the standardized construction process, providing a practical reference for infrastructure, investment, and EPC project management professionals.
1.Preliminary Assessment: Verify External Conditions Before Initiating the Project
Key Tasks:
l Verify land-use planning requirements, ecological protection redlines, and actual electricity and heat demand.
l Assess the natural gas pipeline's supply capacity and available grid connection capacity.
l Prepare a preliminary feasibility study, consult the gas utility and power grid company for initial feedback, and complete the company's internal investment approval process.
Case Study:
A manufacturing company in Jiangsu planned to build an on-site gas-fired reciprocating engine power plant. However, during the initial stage, the company failed to confirm the pipeline gas supply pressure with the gas utility in advance. The pressure shortfall was only discovered during the technical design stage. As a result, the company had to install additional large-scale pressure regulation equipment, increasing the investment by nearly RMB 800,000 and extending the preliminary project schedule by three months.
Key Considerations:
Gas-fired reciprocating engines have strict requirements for gas supply pressure and fuel quality stability. Gas supply conditions must be confirmed at this stage and must not be postponed to later project phases.
2.Project Approval: Obtain Official Project Authorization and Register the Project Code
Key Tasks:
l Prepare a project application report and register the project on the National Online Approval and Supervision Platform for Investment Projects to obtain a project code.
l Apply for project approval from the relevant Development and Reform (Energy) authorities and obtain the official approval document.
Special Note:
If there are major changes to the project location, installed capacity of the reciprocating engines, or core processes, an application for approval modification must be submitted.
Case Study:
A distributed energy project in an industrial park in Zhejiang Province was initially planned to include two gas-fired reciprocating engines. After obtaining project approval, the company added a third unit without authorization. During subsequent environmental protection and grid connection reviews, the project was rejected, and the company was required to restart the project approval modification process.
Key Considerations:
The project approval document specifies the installed capacity of the gas-fired reciprocating engines. Any changes to the number of main units or total installed capacity are considered major project modifications.
Once the project capacity changes, the previously approved environmental impact assessment, energy-saving assessment, and grid connection plan may no longer be applicable. New approval procedures must be completed based on the revised project capacity.
3.Specialized Assessments and External Agreements: Mandatory Regulatory Requirements
Key Tasks:
l Carry out the environmental impact assessment, energy conservation review, safety pre-assessment, and occupational disease hazard pre-assessment in parallel.
l Conduct soil and water conservation assessments and geological hazard assessments as required.
l Sign a formal natural gas supply agreement and complete the review of the grid connection plan.
l Pay particular attention to the control and management of pollutants, including nitrogen oxides (NOx), noise, waste lubricating oil, and condensate from the generating units.
Case Study:
At a gas-fired reciprocating engine energy station in a food industrial park in Shandong Province, experts placed particular emphasis on the low-NOx combustion and flue gas denitrification systems during the environmental impact assessment.
However, the initial denitrification plan failed to meet the local emission limits for NOx at the system outlet. As a result, the technical design had to be revised several times, delaying the environmental impact assessment review by two months.
Key Considerations:
NOx emissions from gas-fired reciprocating engines are a key focus of the environmental impact assessment. The low-NOx emission control measures must be incorporated and finalized during the assessment stage.
4.Site Investigation, Engineering Design and Contract Award: Assessment Requirements Are Binding Constraints
Key Tasks:
l Conduct geotechnical engineering investigations.
l Further develop the feasibility study, preliminary design, and detailed construction drawings.
l Complete the construction drawing review and fire protection design review.
l Select the EPC contractor, project supervision company, main gas engine supplier, auxiliary equipment suppliers, and testing agencies.
5.Construction Permit Application: Complete All Required Procedures Before Commencing Construction
Key Tasks:
l Obtain the required planning permit and construction permit, and complete quality and safety supervision registration.
l Before installation, submit the required installation notifications to the market regulation authorities for special equipment, including gas pressure pipelines and pressure vessels associated with the gas-fired reciprocating engines.
6.On-Site Construction and Installation: Strictly Control High-Risk Gas-Related Operations
Key Tasks:
l Carry out civil foundation works, plant building construction, and installation of gas-fired reciprocating engines, auxiliary equipment, gas pipelines, and electrical systems.
l Complete inspections and acceptance of concealed works.
l Conduct non-destructive testing (NDT) of gas pipelines and pressure piping.
l Implement permit-to-work procedures and strict approval management for hot work in gas areas.
l Collect and organize construction documentation throughout the project.
Case Study:
During the construction of a gas-fired reciprocating engine project at a company in Guangdong Province, a hot work operation on a gas branch pipeline failed to comply with the required risk classification and control measures. The emergency management authorities ordered an immediate work stoppage and rectification following an on-site inspection, resulting in a suspension of nearly 20 days.
Gas systems associated with gas-fired reciprocating engines involve numerous pipelines and widely distributed connection points. Hot work risks must therefore be strictly managed throughout the entire construction process.
Key Considerations:
Gas inlet piping for reciprocating engines is densely arranged. Hot work operations and gas tightness testing are among the most critical aspects of on-site safety management.
7.Commissioning and Trial Operation: Complete Full-System Startup and Full-Load Testing
Key Tasks:
l Carry out commissioning in stages: individual unit testing → subsystem integrated commissioning → complete system startup and ignition, load testing, and grid synchronization testing.
l Complete the grid connection safety assessment before connecting to the power grid.
l Conduct a 72-hour continuous full-load trial operation followed by a 24-hour assessment period, in accordance with applicable standards, and complete all outstanding defect rectification.
Case Study:
At a self-supply gas-fired reciprocating engine power plant in the Yangtze River Delta, a mismatch was identified between the engine synchronization protection logic and the grid protection settings during full-system commissioning. As a result, the project failed to pass the grid connection safety assessment on the first attempt, delaying the planned grid connection.
Key Considerations:
The protection and synchronization parameters of gas engine generator sets must be configured in advance to meet grid requirements.
8.Specialized Inspections and Final Project Acceptance: Complete All Regulatory Compliance Checks
Key Tasks:
l Complete fire protection acceptance, environmental protection self-inspection and public disclosure, safety facilities acceptance, occupational disease prevention facilities acceptance, special equipment inspection and registration, and soil and water conservation and planning verification.
l Organize the final project completion acceptance after all specialized inspections and acceptance procedures have been successfully completed.
9.Grid Connection and Commissioning: Commence Commercial Operation
Key Tasks:
l Submit the grid connection application and complete the verification of metering equipment.
l Sign the grid connection and dispatch agreement. For projects involving surplus electricity export to the grid, an additional electricity purchase and sale agreement must be signed.
l Commence official operation after receiving dispatch authorization, and ensure proper implementation of online monitoring, generator set operation and maintenance, and personnel qualification management.
10.Project Closeout: Archive Completion Documentation and Close Out the Project on the Regulatory Platform
Key Tasks:
l Compile and archive all project documentation, including the feasibility study, project approval documents, specialized assessment and approval documents, engineering drawings, commissioning records, acceptance documents, contracts, and other relevant materials.
l Complete the project closeout procedure on the National Online Approval and Supervision Platform for Investment Projects.
The above outlines the complete process of developing a gas-fired reciprocating engine power plant, from initial planning to grid connection. Following the correct sequence of approval procedures and securing external conditions in advance can help avoid most common project risks and delays.
Disclaimer
The procedures and case studies presented in this article are based on publicly available reports and approval documents relating to domestic gas-fired reciprocating engine distributed energy projects in China. They are provided for general informational and project management reference purposes only and do not replace official approval decisions, applicable regulations and standards, or the conclusions of specialized assessments. Actual project implementation shall be subject to the policies and requirements currently in force in the relevant locality.